Traffic Management Working Group (TMWG)

TMWG update 24 March 2017.

PRINCIPAL CONTRACT

SOUTH

Society Road

Site crossing controlled by stop / go boards as required.

Occasional overhead works, stop / go boards as required.

A904 / B924

Ongoing completion works on A904 / B924 to construct the newly aligned roads and tie-ins.  Two-way traffic on A904 will be maintained at all times until completion.

W/C Monday 27 March 2017, off peak – various white lining works around Echline Gyratory.

B800

North of Ferrymuir roundabout – Minor works to complete footpaths and verges ongoing, some Traffic Management still in place till Spring 2017.

Thursday 30 March 2017, off-peak – lane closures for installation of signs.

A90 between Scotstoun and Admiralty

40mph speed limit and temporary average speed cameras in operation both directions. 

A90 / M90 southbound and northbound between Echline  and Scotstoun

Northbound main line traffic on A90/M90 running on new road layout, southbound now running on newly constructed southbound carriageway.

A90 southbound between Echline and Dalmeny

Until late March 2017 – A90 southbound bus stop closed for bus lane works.

M90 / A90 southbound

Friday 24 March 2017, 2000hrs to 0600hrs – A90 Southbound Closed for Sign Installation on Gantries, Traffic diverted onto Future Public Transport Line, returning to A90 at Dalmeny.  M90 Spur also closed, no access.

M90 / A90 northbound

Saturday 25 March 2017, 2000hrs to 0600hrs – A90 / M90 (Spur) northbound closed for sign installation on Gantries, traffic diverted via Kincardine bridge. Local traffic access to Queensferry via B924.   Forth Road Bridge remains open.

M90 / A90 southbound

Saturday 25 March 2017, 2000hrs to 0600hrs – Lane 2 southbound closed for gantry works.

NORTH

A90 between Admiralty and Scotstoun

40mph speed limit and temporary average speed cameras in operation both directions.

A90 Northbound and Southbound between Ferrytoll and Admiralty

Ongoing until Spring 2017 major works to construct new A90/M90 route for the Queensferry Crossing.   Northbound and southbound carriageways now switched and operating under narrow lanes.

Occasional night lane closures in each direction for works to facilitate traffic management maintenance as required.

W/C Monday 27 March 2017, 0900hrs to 1600hrs – Occasional weaving lane closure southbound for gantry works.

Thursday 30 and Friday 31 March 2017, 2000hrs to 0600hrs – Alternate lane closures north and southbound for surfacing, marking and temporary realignment of traffic lanes.

M90 / A90 Admiralty Interchange

Friday 31 March to Sunday 02 April, 2000hrs to 0600hrs each night – Full closure of southbound merge (on-slip) and alternate lane closures on main line for road / slip road reconstruction works.   Signed diversion in place.

Friday 07 April to Sunday 09 April, 2000hrs to 0600hrs each night – Full closure of southbound merge (on-slip) and alternate lane closures on main line for road / slip road reconstruction works.   Signed diversion in place.

Ferrytoll Gyratory

Traffic now switched to new permanent layout of Ferrytoll Gyratory, traffic management still in place whilst works in area continue.   Pedestrians now diverted under new north underpass.

Ferrytoll Gyratory northbound diverge (off-slip)

Traffic now switched to new northbound public transport link to join Ferrytoll Gyratory.

Ferrytoll Gyratory northbound merge (on-slip) to A90

Traffic now switched away from Castlandhill Road and temporary slip to new northbound merge direct from Ferrytoll Gyratory.  Controlled pedestrian crossing in operation.

Ferrytoll Gyratory southbound merge (on-slip)

Narrowed for retaining wall construction.

Bus lane now commences after southbound merge.

Ferrytoll Park and Ride

Temporary arrangements now in operation while the new bus operating area and turning circle is reconstructed.

0200hrs Saturday 25th March to 0200hrs Monday 27th March 2017 – Closed to enable surfacing of Hope Street.

Castlandhill Road

Occasional stop / go boards in operation for delivery of equipment to site.

As and when required, temporary traffic lights for barrier works.

Ferrytoll Road / King Malcolm Drive

Ongoing until early 2017 – Junction of King Malcolm Drive, Ferrytoll Road and B981 now operating under permanent traffic lights, traffic management still required at east end with Ferrytoll Gyratory.

B981 Hope Street

Major reconstruction works until Spring 2017.

New arrangements in place for access to Park & Ride.

0200hrs Saturday 25th March to 0200hrs Monday 27th March 2017 – Hope Street closed between Ferrytoll Gyratory and Ferryhills Road to enable surfacing operations.

B981 North Queensferry

Temporary Traffic Lights as and when required for landscaping works at Ferrytoll Viaduct.

Non FCBC works

CEC

Ongoing – Burnshot flyover closed over A90.

AMEY

A90

Occasional nightly contraflows during March and April 2017,  2000hrs to 0600hrs each night – Contraflow on Forth Road Bridge for ongoing bridge works, southbound traffic required to divert via Ferrytoll off and on slip roads to rejoin A90.   Times of operation may alter at weekends – please check Amey / Traffic Scotland information channels to confirm.

Thursday 30 and Friday 31 March 2017, 2000hrs to 0600hrs each night  – A92 / M90  J2a southbound merge closed for gantry works, diversion via Halbeath Roundabout.

Please check websites and other media channels.

Further details will be on the Traffic Scotland website  http://trafficscotland.org/ plannedroadworks/