19 May 2026Forth Bridge Management Programme Update
The information below has been provided by Network Rail and is shared for information purposes.
Wind Fence and Steel Repairs
- All works Span 14 completed.
- Span 11 preparation completed, steel repairs around 50% completed to wind fence posts, coatings due to commence.
- Span 15 preparation ongoing with 15 panels completed, steel repairs to wind fence post completed.
Water Management
- Water management works paused other than coating and review of span 11 as detailed. All other works – Wind fence and steel repairs continuing to programme.
- The preparatory works to the bridge deck for the water management project on Span 11 is complete with the coating to be applied.
- Two coating options are being considered, Hammerite and Macropoxy.
- Hammerite coating – 36 nightshifts to complete: assume this will be 6 weeks at 6 n/s per week
- Macropoxy coating – 48 nightshifts to complete: assume this will be 8 weeks at 6 n/s per week
- Both weather dependent. Timescales to confirmation of preferred option likely next week with programme to follow.
- Contractor’s proposal submitted for removal of all loose bitumen from spans 12,13,14 and 15.
Method
- Brush or roller applied, no spraying. Temporary block of weep pipes but nothing else required.
Programme
- The programme for the water management project will need to be adjusted if it proceeds following review and discussion with the community.
